Project Description
Falmouth Docks – Emergency Exit Track Reinstatement
At short notice, we reinstated an emergency exit track at Falmouth Docks that had become unfit for use.
Key details of the project:
- 150 tonnes of tarmac scalpings were relocated from one side of the site to the other.
- The scalpings were spread and compacted to restore the track and fill areas eroded by washout.
- The project was initiated within two days of the initial contact and completed efficiently within the same week.
This swift response ensured the track was promptly restored to a safe and functional condition.
Project Details
WHEN
October 2024
CLIENT
Private Customer
PROJECT TYPE
Track reinstatement